Needs

The client approached Harris Associates to undertake intrusive investigation works and establish the extent of combustible materials contained within the external wall system and monitor and administer the remediation works.

What
We Did

The project comprised the full remediation of the ACM clad external façades which included balconies and decking.
After we undertook assessments and testing, full remediation works were carried out that included:
Removing the eps insulated render façades
Replacing the timber cladding with PIR insulation and an aluminium panelled system
Replacing spandrel panels with aluminium sandwich panels
Timber balcony decking remediation work

We
Provided

Preliminary intrusive site investigations

Project Manager & Lead Consultant

Cost Consultant

Provided Remediation Fund Assistance

Delivered Statutory Compliance Services including securing of planning consent

Coordination of approved inspector and other professional team members

Provided Site Evidencing & Quality Control Inspections by Façade & Construction team

Final
Result

Works ongoing, completing summer 2023 when the pre-existing timber cladding will be replaced with a new wall system and new cladding which achieves European Classification A1 and is compliant with current Building Regulations.

 

Contract Value

£3.8 million