Client
Needs

The client contacted Harris Associated regarding queries about the cladding across their buildings. They required advice and a full investigation ahead of any possible works.

What
We Did

As with many projects, this was a typically challenging project due to the close proximity to the Thames. We undertook facade remediation of the whole development which consisted of multiple buildings with ACM and EPS-rendered facade systems.

We
Provided

Preliminary intrusive site investigations

Coordination of Materials Laboratory Testing

Acting as Project Manager & Lead Consultant

Acting as Cost Consultant

Provision of Remediation Fund Assistance

Provision of Statutory Compliance Services including securing of planning consent

Coordination of approved inspector and other professional team members

Provision of Site Evidencing & Quality Control Inspections by Façade & Construction team

Final
Result

The development has had the whole of the existing eps insulated render system renewed with a new modern, compliant and fully insulated render system. 

Contract Value

£2.8 million